Marina Protection Plan
If you have questions, do not hesitate to call Ed Harwood in the office @ 410-335-3553.
All materials have been ordered. Material barge and second crane will arrive approx. 2/11/11
All will be performed from barges. All material and demo material will be arrive and depart via barge.
All permits are posted next to office door under glass.
1/17/11 pre-construction meeting with Marine Tech.
1/18/11 Loan Settlement w/ lender, signed contract w/ Marine Tech. , Issued Notice to Proceed
1/19/11 Marine Tech. mobilized initial equipment tug, 2 barges, 1 crane
1/20/11 - Commence demo Section 2
1/21/11 - Continue Demo unfasten all deck boards Sect. 2-6
1/24/11 - Commence removal outer panels Sect. 4 / transfer demo material to barge
1/25/11 - Continue Removal/Demo outer panels Sect. 4 / Remove power pedestals from A-Pier
1/26/11 -Weather Day
1/27/11 -Weather Day
1/28/11 -Continue Removal Outer panels Sect. 4
1/29/11 -Commence Removal Outer panels Sect. 3
1/31/11 -Continue Removal Outer panels Sect. 3
2/1/11 - Weather Day
2/2/11 - Weather Day
2/3/11 - Continue removal of Outer Panels at Sections 3 & 4
2/4/11 - Move debris barge to Inner Harbor and offload - crane #1 to harbor
2/5/11 - Arrival of second crane
2/7/11 - No Work - waiting on materials - will resume 2/11 or 2/14
2/8/11 - Continue Demo outer wall Sect. 3
2/9/11 -Demo outer wall Sect. 3
2/10/11 - Complete removal outer wall and pilings Sect. 3
2/14/11 - No Work - high wind
2/15/11 - Arrival of demo and material barge
2/16/11 - Stage barges - Commence driving piles Section 3 - depth limited
2/21/11 - Install vert. piles, Demo 1st 91' of A-Pier decking
2/22/11 - Install Vert. Piles, Re-deck 1st 91' of A-Pier
2/23/11 - Install Vert. Piles, Re-deck 1st 91' of A-Pier
2/24/11 - Install Vert. Piles Sect 3 - stop early equipment down
2/25/11 - No Work - High Winds
2/28/11 - No work - thunderstorms
3/1/11 - Commence batter pile install - Sect. 2
3/3/11 - Install Vert. piles - Sect 4 and 5
3/4/11 - Second barge arrives w second crane - position barges all day
3/7/11 - Stage stringers, girders Sect 2, install Vert. piles Sect 5
3/8/11 - Tug and barge depart for material, Girders Sect 2, Vert piles
3/9/11 - Girders Sect 2, Vert Piles Sect 6
3/10/11 - No Work - Heavy Rain. Extreme tide - power off
3/11/11 - Tug returns. Finish vert piles inside, resume batters in Sect 2
3/14/11 - Batter piles, commence install stringers Sect 2
3/15/11 - Batter piles, Stringers Sect 2, electrician repair panel
3/16/11 - Girders Sect 2, Stringers Sect 2, complete batter piles
3/17/11 - Reposition barges, install 8X8 and stringers Sect 2
3/21/11 - No work - Thunder Storm
3/22/11 - Begin install outer piles Sect 3, 6' OC, continue stringers Sect 2
3/23/11 - Move concrete blocks Sect 3, Stringers and decking Sect 2
3/24/11 - Move concrete blocks Sect 3, Stringers and decking Sect 2
3/28/11 - Cut and attach batter piles Sect. 3, Install Decking Stringers Sect 3
3/29/11 - Cut and attach batter piles Sect. 3, Install Decking Stringers Sect 3
3/30/11 - Cut and attach batter piles Sect. 3, Install Decking Stringers Sect 3
3/31/11 - Cut and attach batter piles Sect. 3, Install Decking Stringers Sect 3
4/4/11 - Finish batters Sect.3, Begin Install outer piles Sect. 4
4/5/11 - Deck Sect. 3, move concrete
4/6/11 - Deck Sect. 3
4/7/11 - Move concrete blocks Sect 3, Stringers and decking Sect 3
4/11/11 - Move concrete blocks Sect 3, Stringers and decking Sect 3
4/12/11 - Complete outer piles Sect. 4, Complete Decking Sect 3
4/13/11 - Install Decking Stringers Sect 4
4/14/11 - Install Decking Stringers Sect 4
4/16/11 - Storm - foreman and crane operator onsite
4/18/11 - Complete Decking/Stringers Sect.4, Clean-up from storm
4/19/11 -Begin Sect.5 - bolt batter piles and begin decking Sect 5
4/20/11 - Continue attaching batters and decking Sect 5
4/21/11 - Continue attaching batters and decking Sect 5
4/25/11 -Continue attaching batters and decking Sect 5-
4/26/11 - Continue attaching batters and decking Sect 5
4/27/11 - Continue attaching batters and decking Sect 5
4/28/11 - no work - severe storms forecast
4/29/11 - Continue Sect. 5 - decking and stringers
5/2/11 - Complete Decking Sect. 5
5/3/11 - Sect. 6 - decking and stringers
5/4/11 - Sect. 6 - decking and stringers
5/5/11 - Complete Decking and Stringers, Sect. 6
5/9/11 - Begin install vinyl skirt in Sect. 6
5/10/11 - Vinyl skirt Sect. 6
5/11/11 - Finish vinyl skirt in Sect.6
5/12/11 - Remove outer panels Sect. 9
5/16/11 - Remove outer panels Sect. 10
5/17/11 - Begin install Vinyl - Sect.7 - North
5/18/11 - Vinyl Sect. 7 - North
5/19/11 - Vinyl Sect. 7 - North
5/23/11 - Vinyl Sect. 7 - North
5/24/11 - Complete vinyl Sect. 7 - North
5/25/11 - Install vinyl skirt Sect. 10
5/26/11 - Vinyl Skirt Sect. 10
5/31/11 - Complete Sect. 10
6/1/11 - Begin Vinyl Sect. 9, Drive piles outer wall Sect. 3
6/2/11 - Vinyl Sect. 9, Drive piles outer wall Sect. 3
6/3/11 - Vinyl Sect. 9, Drive piles outer wall Sect. 3
6/6/11 - Finish Vinyl Sect. 9, Drive piles outer wall Sect. 3
6/7/11 - Piles outer wall Sect. 3
6/8/11 - Complete piles outer wall Sect. 3
6/9/11 - install lower waler Sect. 6
6/13/11 - complete lower waler Sect. 6
6/14/11 - Begin install vinyl Sect. 7 - South
6/15/11 - Vinyl Sect. 7
6/16/11 - Vinyl Sect. 7 - Complete
6/20/11 - Shift barge - Begin Install Upper and Lower walers, Sect. 3
6/21/11 - Upper and Lower walers Sect. 3 and 4
6/22/11 - Finish walers , begin outer wall walers Sect. 3
6/23/11 - Finish upper and lower walers
6/27/11 - Begin Vinyl Install Sect. 3
Please open this PDF file to view a narrative of the work to be completed under the MPP
2/16/11 Barge on Site. Material Barges. 3 barges currently working.
Barges in position to commence build back
2/16/11 Tug positioning material barges outside of A-Pier
A-Pier Vinyl Installation

A-Pier Vinyl Installation

E-Pier T-Head - New piles, girders, stringers and decking.
Vinyl to be installed from top of pier to 4' from mudline.
Cross braces installed under pier.

D-Pier T-Head - New piles, girders, stringers and decking.
Vinyl to be installed from top of pier to 4' from mudline.
Note the cross braces installed under pier for stability.
Outer panels will be removed when vinyl is installed.
A-Pier - Section 1 ( 161') -structural work underway
Decking removed. Deteriorated piles under pier replaced.
Girders, Stringers and decking will be replaced.
Cross braces installed under pier for stability.
D-Pier - notice pile on angle. This is a batter pile.
Batter piles will be added on every other set of verticle pilings
on A-Pier, Sections 3-6. Batters have already been installed in
Sections 9 and 10, D and E-Pier T-heads respectively.
Below are Engineered Drawings for Sections 1-7 and 9-10

Sections 1,2 and 4

Section 3

Section 5
Section 7 - South End
Section 7 - North End
Section 9
Structural work complete
Vinyl to be installed
Section 10
Structural work complete
Vinyl to be installed